Chevron

Geismar Expansion and Improvements Project

Project Highlights

Scroll for more

Related Projects

CF Industries – Port Neal Fertilizer Complex
Renewable Fuels
Fertilizer
Clean Ammonia

CF Industries

arrow_outward
Port Neal Fertilizer Complex
Chevron – Geismar Expansion and Improvements Project
Renewable Fuels
Renewable Diesel

Chevron

arrow_outward
Geismar Expansion and Improvements Project
Archer Daniels Midland Company - ADM Columbus Carbon Capture Project
Renewable Fuels
Carbon Capture (CCUS)

Archer Daniels Midland Company

arrow_outward
ADM Columbus Carbon Capture Project

When it matters most, we’re ready.

info@performance-contractors.com
(225) 751-4156

Chevron – Geismar Expansion and Improvements Project

Scope/Services

Boiler & Furnace Erection & Repairs

Civil

Electrical & Instrumentation

Equipment Assembly & Erection

High Alloy Welding

Hydrotesting

Millwright Alignment Work

Pipe Detailing

Pipe Fabrication

Pipe Installation

Rigging & Heavy Lifts

Site Work & Earth Moving

Soft Crafts

Structural Steel Erection

Industry

Renewable Fuels

Renewable Diesel

Capability

Capital Construction

Module Assembly & Installation

Pipe & Steel Fabrication

Location

Geismar, Louisiana

The Challenge

Performance Contractors, Inc. was contracted by Chevron REG for the construction of the Geismar Expansion and Improvement Project at their facility in Geismar, Louisiana. The expansion increases renewable diesel production by 250 million gallons per year, bringing Chevron REG’s total annual renewable diesel capacity to 340 million gallons.

What We Did Differently

Initially, Performance Contractors was awarded the mechanical scope of work. However, as the project progressed and Chevron REG recognized the strength of the partnership, Performance Contractors was subsequently awarded additional scopes, including the ISBL civil work, piping insulation, and electric heat tracing. In addition, Performance Contractors was selected to execute the full general contractor scope for the Wastewater Treatment Unit, a critical component of the Geismar Expansion and Improvement Project.

Project Total Quantities

  • Piling { 664 EA
  • Civil { 2,584 CY
  • Structural Steel { 2,600 Tons
  • Module Sets { 161 EA
  • Piping { 177,000 LF
  • Welds { 15,443 EA
  • Weld Repair Rate { 1.17%
  • Electrical/Instrumentation { 75, 336 LF
  • EHT { 83,284 LF
  • Insulation { 112,655 SF
  • Architectural Building { 1 EA

‍