Valero / Diamond Green Diesel

LPG to SMR Mechanical Project

Project Highlights

Scroll for more

Related Projects

Archer Daniels Midland Company - ADM Columbus Carbon Capture Project
Renewable Fuels
Carbon Capture (CCUS)

Archer Daniels Midland Company

arrow_outward
ADM Columbus Carbon Capture Project
Diamond Green Diesel 3 – Ecofiner Mechanical Project
Renewable Fuels
Renewable Diesel

Diamond Green Diesel 3

arrow_outward
Ecofiner Mechanical Project
CF Industries – Port Neal Fertilizer Complex
Renewable Fuels
Fertilizer
Clean Ammonia

CF Industries

arrow_outward
Port Neal Fertilizer Complex

When it matters most, we’re ready.

info@performance-contractors.com
(225) 751-4156

Valero / Diamond Green Diesel - LPG to SMR Mechanical Project

Performance Contractors faced a hairpin timeline and shipping obstacles on a global scale — only to deliver an exceptional project with zero near-misses.

Scope/Services

Equipment Assembly & Erection

Millwright Alignment Work

Pipe Fabrication

Pipe Installation

Rigging & Heavy Lifts

Structural Steel Erection

Industry

Renewable Fuels

Renewable Diesel

Capability

Capital Construction

Pipe & Steel Fabrication

The Challenge

This project was important to Diamond Green Diesel because it would allow for the conversion of natural gas into hydrogen through a means of steam reforming. To do this, the equipment scope of the project would be critical. Although this project took place two years after the beginning of the COVID-19 global pandemic, the fallout of this health crisis would continue to linger and to seep into the construction world. Supply chain delays were imminent from the very start of the fabrication process. That meant that our total project duration of five months was reduced to less than two weeks. To achieve this, proper planning and great coordination would be crucial. The first four months essentially served as a pre-turnaround phase. Any activities that could be completed prior to the arrival of the pumps were priority System turnover packages were completed early to ensure a timely turnover.

What We Did Differently

Though many of the tasks had already been completed once before, the same processes occurred the second time around. The checklists and walkthroughs were completed each time in their entirety. Awareness became a critical component of this project. The employees were able to meet this challenge through a combination of specialized training, awareness, and a strong safety leadership team.
‍

Performance Contractors, Inc. was able to complete the project on time, under budget and with zero incidents. With a strong commitment to safety, every employee was able to effectively complete their job tasks and satisfy the client’s request. Proper planning, strong coordination, strategized installation, and specialized training were all key components to finishing this project and adding another job well done to the catalog.

Project Total Quantities

  • Pipe Fabrication { 5,067 LF
  • Pipe Installation { 5.067 LF
  • Steel Erected { 3 Tons
  • Static Equipment Set { 7 Pieces
  • Weld Repair Rate { 0.0%
  • Rotating Equipment { 2 Pieces
  • OSHA Recordables { 0
  • First Aids { 0
  • Near Misses { 0
Item
Quantity
This is some text inside of a div block.
This is some text inside of a div block.