ExxonMobil
Baytown Chemical Expansion Project (BCEP)
Project Highlights
When it matters most, we’re ready.
info@performance-contractors.com
(225) 751-4156
Project Highlights
info@performance-contractors.com
(225) 751-4156

Civil
Equipment Assembly & Erection
Front End Services
Hydrotesting
Millwright Alignment Work
Module Installation
Pipe Installation
Rigging & Heavy Lifts
Structural Steel Erection
Oil, Gas & Chemical
Chemical
Capital Construction
Module Assembly & Installation
Baytown, TX
The scale and complexity of the Baytown Chemical Expansion Project required Performance to coordinate 65 subcontractors while managing an extensive, multidisciplinary construction scope. Work ranged from site development, underground piping, concrete and structural steel to equipment setting, process piping, heavy lifts, cooling tower installation, electrical and instrumentation, hydrotesting, and commissioning and startup assistance. Additionally, a significant component of the project included the dress-out and installation of a 308-foot C6 tower along with nine additional towers.
The project experienced a seven-month “Safe Park” period, so schedule continuity presented an additional challenge. Despite the interruption, the team was tasked with safely remobilizing and completing a 42-month construction effort while maintaining progress toward the original schedule target.
What We Did Differently
Performance maintained a strong emphasis on self-performance and safety throughout execution, self-performing 61% of the project while coordinating the remaining specialized scopes. The project achieved a 0.074 TRIR, and its final 8.75 million work hours were completed without an OSHA recordable, demonstrating the effectiveness of the project’s safety campaigns across an exceptionally large and complex construction effort.